Creative Construction Conference 2016
Initial Analysis, Planning and Calculation of Vertical Transportation in Construction
Dr. Simo Suđić, MSCE, MRICS
Belgrade Waterfront, Belgrade, Serbia, [email protected]
Abstract
The tower crane is one of the major (key) equipment used in high-rise buildings construction. The main challenge encountered in the construction of high-rise buildings is the transportation of construction materials vertically and horizontally to the required or specific areas of the project. To tackle this challenge various equipment such as tower cranes, mobile cranes, hoists, etc., are used and out of all these equipment tower crane plays a vital role in the logistics of construction materials in the construction projects. Investors and General contractors very often use technical and commercial offers from the crane renting companies to make decisions concerning the number of cranes and period of engagement in the project. There is always a commercial and time risk involved to the Clients in the selection of cranes based on the offers from crane companies, as mostly these crane companies would try and sell what they have in their hand opposed to the most time and cost efficient options for the project. The main reason for that risky approach is a lack of standardized methodologies for the tower crane productivity calculation and decision-making on the selection of models for different proposed solutions by specialists. Identifying optimal number, location and duration of operations on the site are the major factors that can reduce the possibilities of the project outrun over the budgeted time and cost by increasing the productivity and lessen the time of construction. Often tower cranes operate with overlapping works zones, and under time, cost and labor constraints. Therefore, proper planning to be considered, while choosing a tower crane, based on different production parameters such as optimal space per worker, concrete production per crane or worker, lifting time, crane booms overlapping, health and safety measures, and crane operators well-being during the crane operation with maximum visibility to the work areas. In this paper, the methodologies for the number of crane calculation and their optimal positioning in three different construction phases are discussed - underground structures, above ground structure, façade, MEP and finishes work. CPM planning techniques (Primavera P6 software) is used for the proposed model, considering leveling and optimizing of crane usage. An actual case example is provided to demonstrate the planning model for the selection and positioning of tower cranes.
Keywords: construction, optimization, planning, tower crane
1. Introduction
A typical high-rise building construction involves lifting materials of different load size, type and weight, within the determined time with logistics, commercial, health & safety, administrative, programme and other constraints. For instance, let's consider concreting works, which are always in the critical path of high-rise construction projects, to which tower cranes are the most key logistic equipment which defines the programme certainty of these works. Therefore, tower crane needs to be planned appropriately. At present, planning for tower crane operations is mostly performed intuitively and based on experience (Hasan S. et al., 2010).
For any construction project, one of the most important documents are the general construction and logistics plans. General construction plan identifies number of cranes with their position. In authors experience, any delays during the preconstruction period (design, planning approvals, procurement) will be cascaded to the construction period and the project will require a mitigation strategy of all these delays within the construction period. In that case, the best option to reduce or mitigate delays within construction period is by increasing or optimizing number and position of cranes, along with the corrective measure and increasing of required resources (labors, material, other equipment etc.) will increase the production thus reducing the time and delay. In this paper author has analysed a case study from one of the large commercial project with possible suggestions for the improvement and optimization of tower cranes.
469

2. Methodology
The methodology outlined below was employed to determine necessary tower cranes and their optional location and time for a large commercial construction project. In practice, a tower crane is selected based on the maximum load needs to be lifted, size of the load, site layout, and the reach or capacity (Hasan S. et al, 2010).
Site organization with optimum resources to maximize production is the best way to reduce construction cost. Efficiency of concrete works mostly depend on:
 number, types and position of tower cranes;  number, specialties of productive workers on site;  quantity and type of formwork;  availability of materials and supply ‘just in time’.
It is tough to calculate maximum production per worker, because of technological sequences, idle time, weather conditions, skills and physical condition of workers etc. (Hasan et al., 2010) calculated, based on production control, following data presented in the table 1:

process name
inspection crane 1 crane 2
installation L1 installation L2

available time (min) 480 480 480 480 480

cycle time (min) 13 15 15 20 20

active (min)
429 255 240 340 320

idle (min)
51 225 240 140 160

% of utilization
89,38% 53,13% 50,00% 70,83% 66,67%

Table 1: Calculation of percentage of crane utilization (Hasan et al., 2010)

Based on percentage of utilization, standard construction method analysis and statistical data from three construction sites in Russia during different weather conditions, above results were calculated. It is found that maximum percentage of utilization per crane is only 53,13%. The above simple analysis was based on statistical data of monthly concrete poured (m³) and number of skilled and unskilled labors assigned to concrete works (reinforcement, formworks and concreting works).
In general, tower crane utilization in construction job sites is estimated to be 50% to 80% (Hasan et al, 2013; Gillis & Telyas, 2013; Kay, 2001, Rosenfeld & Shapira, 1998). Reducing the crane lifting cycle or maximum utilization of tower crane not only increase the crane productivity but also helps in reduction of total project duration
The tower crane during its operation is the most key equipment in the logistics of the critical path activities. Saving in crane operations will have its impact on two major operational factors. First, saving in crane operation will shorten crane cycle time. Second, higher labor productivity is expected due to shortening of the crane operation.
Saving related to the crane operation cost can be divided into four categories:

1. Annual ownership cost: this is a cost of buying a crane throughout its useful life span; 2. Operation cost: included fuel, maintenance, license fees, and insurance; 3. Operator cost: this is salary of the crane operator; 4. Labor cost: cost of the laborer working directly with the crane.

470

Below, in the table 3, is presented crane operational time on site. Basically, due to the fact that tower cranes stay longer in the project and as their rental rates and mobilizing costs are high. Therefore it is not economical to rent a tower crane for the projects with longer project duration (Rosenfeld & Shapira, 1998; Sullivan et al., 2009).
For the tower cranes production calculation, it was used average production rates from author previous experience, presented in table 2:
 Optimal number of workers per crane during concrete works ≈ 70 workers;  Winter productivity per worker ≈ 16 m³/month (Russia);  Summer productivity per worker ≈ 23 m³/month (Russia);
From the previously defined data, average production per crane are:
 Production per crane underground (substructure) – 1200 m³/crane/month;  Production per crane above ground (superstructure) – 1500-1700 m³/crane/month.

Construction site 1 (commercial 185,000 m³ of concrete)
Construction site 2 (commercial 210,000 m³ of concrete)
Construction site 3 (commercial 320,000 m³ of concrete)

jul

aug sept

oct

nov

dec

8450 8920 9650 9790 6140 5920

375 395 425 465 375 360

9230 9610 8420 8890 7290 7140

390 400 385 395 440 420

12610 14100 14340 12220 11600 10650

555 610 615 580 690 690

Table 2: Concrete production and number of workers on site
A concrete pouring plan is very essential to be defined and it has to be a part of project logistics plan, general construction plan and concrete works method statement. It can be prepared based on concrete quantities from schematic design which will form the basis for initial level 2 time programme. Concrete foundations and frame are always on critical path, and which are subjected to many constraints such as logistics, availability of concrete plants, traffic, pumps, tower cranes, etc. Tower cranes are primarily are used for the logistics of reinforcement, formwork, brickworks, concrete columns and concrete pouring, and for lifting other materials. In this paper two optimization steps are analyzed - determination of minimal number of tower cranes and optimizing location of tower cranes in order to minimize potential conflicts between tower cranes and other facilities. Each crane has his load chart that specifies lifting capacity. The maximum capacity is always obtained by the shortest crane’s operating radius. (Irrizary and Karun, 2012).
For the proper planning of crane utilization, it is very important to define various phases of construction. Usually, underground and above ground construction are different from the point of view of tower cranes usage. In that case, the best option to reduce or mitigate delays within construction period is by increasing or optimizing number and position of cranes, along with the corrective measure and increasing of required resources (labors, material, other equipment etc.) will increase the production thus reducing the time and delay.
A proper general construction plan should define the optimal position of the tower cranes. According to (Tam et al., 2001) and (Zhang et al., 1999) in order to lift load at supply point (S) with the weight w, tower crane should be placed within a circle centered at S and with lifting radius R, where R is the minimum of the tower crane’s jib length (Cr) and operating radius (r) obtained from load chart. In the proposed model, it is possible to consider more than one demand point for each supply points. In reality, there may be more than one feasible area within a construction site. A tower crane can handle two tasks, if it is located within the area of intersection between than (fig 1).

471

Fig 1: Feasible task area for supply (S) and demand (D) points (a) single task (b) multiple task (adopted from Irizarry and Karan, 1999)
If there is no overlap between tasks, then a single tower is not enough to handle both tasks. The geometric closeness of tasks can be measured by the size of the overlapping area (the larger overlapping area, the greater closeness). A larger overlapping area between two or more cranes may result in longer presence of the cranes in the shared area and therefore there will be a higher risk of collision (Shapira and Simcha, 2009b). Thus, the model searches for places with minimum overlapping area between cranes and their surrounding facilities.
Fig 2: Task closeness (adopted from Zhang et al. 1999)
3. Case Study In this case study Tower Crane Management on a commercial project in Moscow, Russian Federation is
analyzed. The project consists of 420,000 m² GFA (hotel, office buildings and residential with 2 to 3 floors of underground parking). The project was financed by international bank and the Main contract was appointed under cost plus (open book) guaranteed maximum price contract. Time programme was previously agreed, and was exposed to many risks due to challenges in logistics, weather conditions, subcontractor performance and coordination etc.
Employer (Investor) wanted to optimize the crane usage for their maximum benefit and they also wanted it to be dismantled within two months after the completion of concrete works.
Tower cranes are intensively used during structural – concrete works, for vertical transportation of reinforcement, formwork and sometimes for concreting of walls and columns. Construction of underground and above ground is different because of more activities which is performed in parallel with concrete works (waterproofing, excavation, dewatering, protection of foundation pit) below level ±0,00, and programme of works depend on coordination, and technological links between activities. Tower cranes for construction above level ±0,00 are mostly used for concrete works and it is also used for the logistics of other materials for brickwork partitions and façade in parallel depending on the availability. For the optimal use of tower cranes, project phases should be appropriately defined and based on that number of cranes for each phase to be planned.
472

Table 3 – Number of crane calculation based on concrete plan and proposed production rates
Maximum quantity of concrete planned to be poured monthly on that construction site was 8,000 m³ for the below ground works. Simple calculation based on production rates proposed in the above chart gives us the optimum number of cranes to be used is five with number of people – 350 productive skilled workers to achieve the planned monthly concrete works of 8000 m³. In actual additional 2 cranes were installed to achieve the planned concrete plan.
For the approximate estimation of crane usage duration, planning tools like, Microsoft Project, Primavera, Asta Power Project etc. are used.
According to the contract milestone table and duration, time programme was prepared using software Primavera Enterprise P8.2 with works breakdown structure (WBS) as belowground and above ground. Concrete quantities were loaded as resources, with linear distribution as shown in the fig 3 and histogram of concrete to be poured monthly is obtained. This plan is very similar to one presented in the table 3. Also, the crane allocation is shown in the programme as ‘level of effort’ activities as separate WBS.
In presented case concrete distribution was distributed as linear, but there is possibility to set distribution as front or back loaded, bell shaped, normal distribution, etc. In the table 3 it’s been already presented the concrete plan with crane calculation and number of people required.
Maximum concrete poured per month = number of cranes x number of workers per crane [70] x production/worker/month (calculation on the above part of table 3).
Number of cranes = square meter of slabs poured per month / average production per crane (calculation on the below part of table 3).
473

Fig 3 – Planned concrete production and crane loading during concrete works
Generally, in the table 3 and fig 3 shows the same excercise, but for better understanding and presentation it is proposed to calculate concrete plan using planning and scheduling software in fig 3, and then it is exported to Microsoft Excel table, as in the table 3 for the calculation of concerete plan, labor and number of cranes required.
Fig 4 – Time programme and crane engagement per building
On the Fig 4 is shown in black color planned period for construction, and in pink color planned period of crane installation on site, similar presentation as on fig 3.
Renting company proposed number of cranes and layout presented on fig 5. Using methodology of supply and demand points, conflicted areas, and calculation of production rates, it was concluded that number of cranes is very high and there are many conflicted areas between cranes.
A large overlapping area between two or more cranes may result in longer presence of the cranes in the shared area and therefore there will be a high risk of collision between the cranes. Even though with this number of cranes, high productivity is possible, but there will be low percentage in utilization of individual crane. Also, cost of installation and dismantling of cranes in this case is very high. Therefore the crane company’s proposal was rejected.
474

Fig 5 – Proposed crane layout by renting company
For phase 2, which is point of concern in this paper, crane company has proposed nine cranes but according to calculation in table 3 with assumptions sufficient number of cranes to achieve programme is 6,3 (7). General contractor analyzed crane company’s layout, position of buildings (demand points), supply points, and proposed the tower crane strategy to achieve the project programme.
Fig 6 – Proposed tower cranes for commercial project by crane renting company
Calculation in table 4 is overall crane usage on construction site, based on concrete works programme. From that calculation, it is possible to define cost of cranes and to analyse possible solutions for crane usage. That calculation is based on very aggressive approach of cranes being dismantled 2 months after the completion of concrete works.
475

Table 4 – Overall crane engagement per building
After analyzing the proposal from crane renting company (shown on fig 6) and calculation presented in table 3 and construction time schedule, decision has been made to organize vertical transportation with tower cranes, as in fig 7. Although calculation shows it requires only 7 cranes but after expert analysis with all possible assumptions, decision is been made to install 8 cranes for the construction of phase 2. The main reason for installation one additional crane is due to restricted position of supply points, and to be on the safe side in case of any unknown risk and to reduce time for construction. With this strategy utilization of tower cranes has been made higher than average referenced in the literature.
Fig 7 – Construction plan with position of tower cranes for phase 2
4. Conclusion This overview and analysis is attempt to present and clarify main topics related to crane analysis, calculation
and management in high rise construction. Case study based on previous project experience should be analysed and confirmed at the end of the project with statistical data collected during execution period. Proposed approach of number of cranes calculation can be improved with different productivity rates, which depend on specifics of construction site, building type, climate conditions, technological and organizational factors, etc. Right possition of crane should be defined considering supply and demand points, and that is mostly geometrical approach. This problem always should be analysed from planning perspective as productivity and duration of crane usage on construction site make great impact over many aspects of the construction process.
476

References
Emsley M.W. "A model to optimize single tower crane location within a construction site", A Doctoral Thesis, Loughborough University Irizarry J., Karan E. (2012) "Optimizing location of tower cranes on construction sites through GIS and BIM integration", Journal of
Information Technology in Construction, Vol 17 2012, pp. 351 – 366 Hasan S., Al-Hussein M., Gillis P. (2010) "Advanced simulation of tower crane operation utilizing system dynamics modeling and lean
principles", Proceeding of the 2010 Winter Simulation Conference, pp. 3262-3271 Tork A.Z. (2013) "A real time crane service scheduling decision support system (CSS-DSS) for construction tower cranes", A Doctoral
dissertation, University of central Florida, Orlando, Florida
477